Trakonyx markTRAKONYXGet started
Trakonyx mark

Earned value management

Earned value management software for portfolios, programs and projects

Trakonyx calculates SPI, CPI, SV, CV, EAC, VAC and TCPI from your approved baseline, planned percent complete at a chosen status date, and actual cost taken from approved timesheets — then rolls the results up the portfolio hierarchy.

The metrics it calculates

Every project dashboard shows the full set, recalculated whenever the plan, timesheets or change requests change.

MetricFormulaHow to read it
SVSchedule VarianceEV − PVNegative means the project has delivered less value than the plan called for by the status date.
CVCost VarianceEV − ACNegative means you have spent more than the value earned.
SPISchedule Performance IndexEV ÷ PVBelow 1.0 is behind schedule; the dashboard flags projects under 0.9.
CPICost Performance IndexEV ÷ ACBelow 1.0 is over budget; used for the independent forecast at completion.
EACEstimate at CompletionBAC ÷ CPIForecast total cost if current cost efficiency continues.
VACVariance at CompletionBAC − EACExpected budget surplus or overrun at close-out.
TCPITo-Complete Performance Index(BAC − EV) ÷ (BAC − AC)The efficiency the remaining work must run at to still hit the budget.

PV = planned value, EV = earned value, AC = actual cost, BAC = budget at completion.

The four inputs everything is built from

PV

Planned Value

The budgeted cost of the work the baseline says should be done by the status date. Trakonyx derives it from planned % complete against the approved baseline.

EV

Earned Value

The budgeted cost of the work actually completed: BAC × actual % complete, rolled up from activities to phases to the project.

AC

Actual Cost

What the completed work really cost — approved timesheet hours at the resource cost rate, plus posted non-labour actuals.

BAC

Budget at Completion

The authorized total budget, including the effect of every approved change request.

A worked example

The defaults describe a 12-month delivery with an approved budget of SAR 1,200,000 reviewed at month 6. Replace PV, EV, AC and BAC with your own project's figures and every metric recalculates instantly.

MetricWorkingResultWhat it means
SVSAR 504,000 − SAR 600,000-SAR 96,000Behind plan — less value earned than the baseline called for.
CVSAR 504,000 − SAR 560,000-SAR 56,000Overspent against the value delivered.
SPISAR 504,000 ÷ SAR 600,0000.84Progressing at 84% of the planned rate.
CPISAR 504,000 ÷ SAR 560,0000.90Earning SAR 0.90 of value per SAR 1.00 spent.
EACSAR 1,200,000 ÷ 0.90SAR 1,333,333Forecast cost at close-out if current cost efficiency holds.
VACSAR 1,200,000 − SAR 1,333,333-SAR 133,333Expected overrun — the trigger for a change request.
TCPI(SAR 1,200,000 − SAR 504,000) ÷ (SAR 1,200,000 − SAR 560,000)1.09Remaining work must run at 1.09 efficiency to still land on BAC.

Where the numbers come from

Baseline vs. actual drift

Approved baselines store planned start, finish and cost per phase and activity. Gantt bars show baseline against actual dates so slippage is visible before it reaches the cost curve.

Planned % as of a status date

Each user sets a status date; planned percent complete is recalculated from the baseline for that date, so PV and SPI reflect the reporting period rather than today.

Actuals from approved timesheets

Approved time posts to activity actuals at the resource cost rate, so AC comes from the same records used for utilization — no parallel spreadsheet.

Change requests fold into the baseline

Approved change requests shift schedule, budget and resources, then re-baseline with PMO approval so EVM stays measured against an authorized plan.

Portfolio and program roll-up

SPI and CPI aggregate up the portfolio → program → project hierarchy, with node-level permissions and masking of financial fields for users without cost access.

AI variance narratives

AI drafts the executive brief: which activities drive the variance, the trend since the last period, and the recommended corrective action — in English or Arabic.

Put earned value on every project

Import or build the plan, approve a baseline, log time — the EVM dashboard follows automatically for Waterfall, Agile and Hybrid delivery, in English or Arabic.

Create your workspace
Visit PMO-ConnectPMO-Connect platform logo