Earned value management

Earned value formulas: a practical guide to SV, CV, SPI, CPI, EAC and TCPI

Every core earned value management formula in one place — what each one measures, how to read the result, and the mistakes that make the numbers misleading.

Trakonyx guide · about 6 min read

What earned value management measures

Earned value management (EVM) compares three things at a single status date: the work you planned to have done, the work you actually did, and what that work cost. Expressing all three in the same currency lets scope, schedule and cost be read together instead of in separate reports.

The formulas below are the standard EVM set. They only produce meaningful results when the inputs come from an approved baseline and one agreed status date.

The four inputs

BAC (budget at completion) is the total approved budget. PV (planned value) is the budgeted value of work scheduled to be complete by the status date. EV (earned value) is the budgeted value of work actually complete. AC (actual cost) is what was really spent on that work.

EV is not what you spent and not elapsed time — it is the budget of the work finished. If a SAR 100,000 activity is 40% complete, its EV is SAR 40,000 whatever it actually cost.

Variance formulas

Schedule variance SV = EV − PV. Negative means less work is done than planned, measured in money rather than days.

Cost variance CV = EV − AC. Negative means the completed work cost more than its budget.

  • SV = EV − PV (below zero: behind schedule).
  • CV = EV − AC (below zero: over budget).
  • VAC = BAC − EAC (below zero: forecast overrun at completion).

Performance index formulas

Schedule performance index SPI = EV ÷ PV. Cost performance index CPI = EV ÷ AC. A value of 1.0 is on plan; below 1.0 is behind schedule or over budget; above 1.0 is ahead or under.

Indices let you compare projects of different sizes. In Trakonyx, the portfolio dashboard flags projects whose SPI falls below 0.9, and SPI and CPI roll up through portfolio, program and project.

Forecasting formulas: EAC, ETC and TCPI

The most common estimate at completion is EAC = BAC ÷ CPI, which assumes current cost efficiency continues. Other recognised variants are EAC = AC + (BAC − EV), assuming remaining work runs at budget, and EAC = AC + (BAC − EV) ÷ (CPI × SPI), when schedule pressure also affects cost. Choose the one that matches your assumption and say which you used.

Estimate to complete ETC = EAC − AC is the money still needed. To-complete performance index TCPI = (BAC − EV) ÷ (BAC − AC) is the cost efficiency the remaining work must achieve to finish on the original budget; a TCPI well above 1.0 signals the budget is unlikely to hold.

A quick worked example

Illustrative figures only: BAC = SAR 1,200,000, PV = SAR 600,000, EV = SAR 504,000, AC = SAR 560,000. Then SV = −SAR 96,000, CV = −SAR 56,000, SPI = 0.84, CPI = 0.90, EAC = BAC ÷ CPI ≈ SAR 1,333,333, VAC ≈ −SAR 133,333, ETC ≈ SAR 773,333 and TCPI = 696,000 ÷ 640,000 ≈ 1.09.

Our article on earned value on Saudi projects walks through how to interpret these same numbers and turn them into actions.

Common mistakes

Mixing status dates between PV, EV and AC; using optimistic percent-complete estimates as EV; ignoring accrued costs that haven't been invoiced; and dividing by zero when PV or AC is still zero early in a project. Each one makes the indices look precise while being wrong.

Try your own figures in the earned value calculator on the Trakonyx EVM page. Inside a workspace, Trakonyx calculates PV from the approved baseline for each user's status date and uses approved timesheets towards actual cost.

These are suggested professional practices, not legal advice or confirmation of compliance. Review applicable regulations, contracts and your organisation's approved delegations with specialists before adopting any procedure.