Earned value on Saudi projects: reading SPI and CPI in Saudi riyals

A worked example linking project progress and cost to the baseline — and explaining what the indices tell you and what they cannot.

Trakonyx guide · about 5 min read

Why percent complete isn't enough

A project at 42% complete may look healthy, but the verdict changes if the plan called for 50% by the status date. Spending may be below the total budget yet above the value of the work actually done. Earned value management links scope, schedule and cost to expose these gaps.

Start with an approved baseline, a single status date and a clear way to measure progress. Don't feed an optimistic estimated percentage into the calculation and then treat the result as independent proof of project health.

The four inputs

Budget at completion (BAC) is the total approved budget. Planned value (PV) is the value of work that should have been done by the status date. Earned value (EV) is the value of work actually completed, at budget rates, and actual cost (AC) is what that work cost.

Align the period and the work covered across all four values. On contracts where invoices lag, the absence of a recorded invoice doesn't mean the work cost nothing; agree how costs are accrued with finance before interpreting the cost index.

Worked example: a SAR 1.2 million budget

Take a 12-month project with an approved budget of SAR 1,200,000. At the end of month six, planned value is SAR 600,000, earned value is SAR 504,000 and actual cost is SAR 560,000. The example is illustrative and does not represent customer data.

Schedule performance index SPI = EV ÷ PV = 0.84: the work delivered equals 84% of the value planned to date. Schedule variance SV = EV − PV = −SAR 96,000. That variance is measured in value, not in days of delay.

Cost performance index CPI = EV ÷ AC = 0.90: each riyal spent delivered SAR 0.90 of planned value. Cost variance CV = EV − AC = −SAR 56,000, indicating an overrun on the work completed.

Forecasts assume performance continues

If current cost efficiency continues, EAC = BAC ÷ CPI ≈ SAR 1,333,333, and variance at completion VAC = BAC − EAC ≈ −SAR 133,333. That is the output of a simplified model, not a guarantee the project will finish at that cost.

One-off work, price changes or a correction in how costs are recorded can shift the result. Review the forecast assumptions and remaining work before recommending a budget increase. If planned value or actual cost is zero, the related ratio cannot be calculated.

Turn the index into action

Find the activities driving the variance and verify their data with the delivery owner. Separate productivity problems from approval delays and scope change, then set an action, owner and date. Don't rebaseline just to hide poor performance.

Use the earned value calculator on the Trakonyx EVM page to try your own numbers, then tie the review to the baseline, change requests and approved timesheets inside your workspace.

These are suggested professional practices, not legal advice or confirmation of compliance. Review applicable regulations, contracts and your organisation's approved delegations with specialists before adopting any procedure.